| 15 | | * 23.11.05: Start of the project design (0% of avalable time) |
| 16 | | * 30.11.05: Start of implementation (10% of avalable time) |
| 17 | | * 21.12.05: Mini presentation of the state of the project (40% of avalable time) |
| 18 | | * 11.01.05: Project freeze: debug and documentation session (70% of avalable time) |
| 19 | | * 25.01.05: Big project presentation (100% of avalable time) |
| | 15 | * 23.11.05: Start of the project design (0% of available time) |
| | 16 | * 30.11.05: Start of implementation (10% of available time) |
| | 17 | * 21.12.05: Mini presentation of the state of the project (40% of available time) |
| | 18 | * 11.01.05: Project freeze: debug and documentation session (70% of available time) |
| | 19 | * 25.01.05: Big project presentation (100% of available time) |